| .. _tunnels: |
| |
| Tunnels |
| --------- |
| |
| Tunnels share a similar property to recursive routes in that after applying the |
| tunnel encapsulation, a new packet must be forwarded, i.e. forwarding is |
| recursive. However, as with recursive routes the tunnel's destination is known |
| beforehand, so the recursive switch can be avoided if the packet can follow the |
| already constructed data-plane graph for the tunnel's destination. This process |
| of joining to DP graphs together is termed *stacking*. |
| |
| .. figure:: /_images/fib20fig2.png |
| |
| Figure 11: Tunnel control plane object diagram |
| |
| Figure 11 shows the control plane object graph for a route via a tunnel. The two |
| sub-graphs for the route via the tunnel and the route for the tunnel's |
| destination are shown to the right and left respectively. The red line shows the |
| relationship form by stacking the two sub-graphs. The adjacency on the tunnel |
| interface is termed a 'mid-chain' this it is now present in the middle of the |
| graph/chain rather than its usual terminal location. |
| |
| The mid-chain adjacency is contributed by the gre_tunnel_t , which also becomes |
| part of the FIB control-plane graph. Consequently it will be visited by a |
| back-walk when the forwarding information for the tunnel's destination changes. |
| This will trigger it to restack the mid-chain adjacency on the new |
| *load_balance_t* contributed by the parent *fib_entry_t*. |
| |
| If the back-walk indicates that there is no route to the tunnel, or that the |
| route does not meet resolution constraints, then the tunnel can be marked as |
| down, and fast convergence can be triggered in the same way as for physical |
| interfaces (see section ...). |